Aug 13 2020

The 2020 ISP: A Lonely Planet guide for transmission

On 30 July the Australian Energy Market Operator (AEMO) published its biennial Integrated System Plan (ISP), which recommended about $10 billion of interconnect projects be developed over the coming 20 years.[i]  There have been many summaries written about its 631 pages and megabytes of supporting spreadsheets, but is there something the press has overlooked? We investigate further.

What the ISP reported

According to the ISP, the Optimal Development Path is shown in the following diagram:

Figure 1: The Optimal Development Path for the National Electricity Market

  Source: AEMO, 2020 ISPii

Under the Central Scenario, the additional interconnector capacity installed by 2036-37 is in the order of 6GW. In common with its predecessor, the 2018 ISP,[ii] the 2020 ISP does not present an easily accessible summary of the optimal development path’s improvement in transfer capacity (and their associated costs), so the Australian Energy Council (AEC) compiled the following table from Appendix 3:

Costs

As can be seen from the table above there is a wide range of costs for all the projects listed.  The fundamental assessment of projects’ viability is reliant on benefits exceeding costs, and when there is such a broad range, there is increased risk projects cannot be justified and, given there are dependencies between projects, subsequent projects should not be recommended either.

A prime example of the difficulty in obtaining a firm cost estimate is Project EnergyConnect.

Based on a capital cost of $1.53 billion, on 24 January the AER determined the Regulatory Investment Test for Transmission (RIT-T) for the project was satisfied.  The ISP has modelled the cost at $1.99 billion (more than 30 per cent higher) and ElectraNet has announced that updated cost estimates will be available by September.[iii]

Other observations

AEMO is to be applauded for the significant consultation it conducted in the development of the 2020 ISP.  However, the breadth of material to review and the time commitment needed to participate in the process and scrutinise the inputs, assumptions, specialist reports and draft findings may well have deterred all but larger market participants from contributing to the debate.

This suggests the Australian Energy Regulator (AER), which is already involved in the scrutiny of the ISP via its Guidelines to make the Integrated System Plan actionable,[iv] and also the RIT-T Application Guidelines,[v] should become involved in the review of the ISP prior to publication to ensure:

  • consultation with stakeholders has been properly considered;
  • assumptions are appropriate;
  • methodologies used are defensible; and
  • forecasts are reasonable.

For example, the discount rate used in all the NPV calculations is based on the RIT-T guidelines,[vi] however the discount rate used for the Slow Change scenario has been varied by 2.0 per cent to account for “the more challenging economic environment”.  Is this an appropriate variation?  Perhaps there is heightened risk in the Fast Change scenario which would warrant a higher discount rate, too?

The AEC suggests that the AER is the best body to consider these issues. 

Conclusions based on weighting scenarios and sensitivities

The AEC has been critical in the past of scenario weightings unreasonably skewing conclusions,[vii] since extraordinarily high (or low) scenario outcomes can, even with small weightings, have a disproportionate effect on the choice of the best development path.

The ISP continues this practice, and has now added four distinct market event sensitivities:

  • Early coal closure;
  • NSW’s Central West Orana REZ;
  • Snowy 2.0 delayed; and
  • Industrial load closures.

While it’s common practice in analysis to include sensitivities to show how quickly results would change if a single, key assumption changed, the sensitivities included in the ISP have been treated as scenarios, with their combined weighting being 40 per cent in the derivation of the weighted nett market benefits.

While excluding the sensitivities from the weighted averaging does not change the first-ranked development path (Central Least-Cost + Marinus Link Early Works), it does change the ranking of other development paths.  For example, the Central Least-Cost development path, which one would assume is the baseline preferred development path, falls to fourth in the rankings.

Where’s the gas?

In order to determine what transmission is justifiable, the ISP must model a least-cost generation future and, as a result of the planned closure of older power stations, the ISP identifies a need for as much as 11.8GW of new dispatchable capacity by 2039-40.[viii]  A lack of new coal and combined-cycle technology was to be expected in a high renewable energy future.  What was particularly surprising was that none of the generation scenarios included new peaking gas-fired technology.

This modelling result comes about mainly due to a competition between the price of new gas-fired peaking plants versus the cost of storage, in particular what the ISP describes as “shallow” battery storage; that which can hold 4 hours of energy, i.e. enough to cover an evening peak when the sun goes down.  AEMO consulted heavily on input costs and received very optimistic views on the present and future cost of batteries.[ix]  AEMO explains how these compete with gas in the following simplified chart.

Figure 2: Breakeven cost analysis – new GPG versus battery capacity for providing daily peaking support

 Source: Source: AEMO 2020 ISP[x]

This suggests that if you can store zero price surplus renewable energy, it is already cheaper to invest in a battery to meet a 4 hour peak than to build a peaking gas plant fuelled by $9/GJ gas – which is not far above today’s gas prices.  And, by 2030, battery storage will be cheaper at any price of gas.

This is a surprising claim and seems at odds with the current market that is still investing in peaking gas.[xi]  The ISP’s results depend entirely on the quality of the input data and, whilst these inputs were openly consulted, the outcome of that consultation still needs to remain grounded in defensible observation rather than aspiration.

Note that despite these optimistic views on storage, the ISP models the NEM’s existing large gas fleet to remain largely in place through the scenarios’ planning period, and actually increases its generation compared to today (See figure 3).

Figure 3: Projected GPG Generation across a range of reference years

 Source: AEMO ISP[xii]

In the end, however, modelling of the forms of dispatchable capacity is just that – a model.  It will be up to market investors, paying real costs for technologies, to decide what is truly the best way to supply customers during lulls in renewable energy, and the death of new gas peakers may yet be greatly exaggerated.

Actioning the ISP

The AER is currently consulting on Guidelines to make the Integrated System Plan actionable, and published its draft decision on 15 May.[xiii]  The guidelines set out the cost benefit analysis and forecasting best practices which AEMO should conduct when developing the ISP, as well as how projects identified in the ISP may expedite their assessment under the RIT-T.

The AEC is supportive of streamlining assessment processes by removing duplication and unnecessary steps, but, as previously expressed,[xiv] it is important that rigorous assessment of nett benefits be continued by the AER, to ensure that the likely market benefits outweigh the cost to consumers.  It is also essential that a fair playing field exists between new generation and regulated transmission, for the confidence of market investors, whose returns may be otherwise impaired.

Conclusion

The 2020 ISP is a monumental work by AEMO, and is important for setting out a likely (but not guaranteed) version of the market and transmission in the future.  It is essential that readers regard the document as a guide, and support the AER in ensuring that the economics of individual projects are assessed rigorously.


[i] https://www.aemo.com.au/energy-systems/major-publications/integrated-system-plan-isp/2020-integrated-system-plan-isp

[ii] https://www.aemo.com.au/energy-systems/major-publications/integrated-system-plan-isp/2018-integrated-system-plan-isp

[iii] https://aemo.com.au/consultations/current-and-closed-consultations/pec-stakeholder-update

[iv] https://www.aer.gov.au/networks-pipelines/guidelines-schemes-models-reviews/guidelines-to-make-the-integrated-system-plan-actionable

[v] https://www.aer.gov.au/networks-pipelines/guidelines-schemes-models-reviews/rit-t-and-rit-d-application-guidelines-2018

[vi] ISP, p.36

[vii] See, for example, https://www.energycouncil.com.au/analysis/riverlink-don-t-spend-the-savings-all-at-once/

[viii] ISP, Appendix 4, p.15, Table 4, Central Scenario

[ix] The final CSIRO Generation Cost report is here: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/scenarios-inputs-assumptions-methodologies-and-guidelines#workbook-archive. The direct link to the report is:  https://publications.csiro.au/publications/#publication/PIcsiro:EP201952/

[x] See ISP, page 55, Figure 18.

[xi] See https://www.energyaustralia.com.au/about-us/media/news/design-nod-puts-tallawarra-expansion-path-final-decision

[xii] See ISP page 56, figure 19

[xiii] Available at https://www.aer.gov.au/networks-pipelines/guidelines-schemes-models-reviews/guidelines-to-make-the-integrated-system-plan-actionable/draft-decision

[xiv] See, for example, https://www.energycouncil.com.au/media/16497/20190621-aec-converting-the-isp.pdf

Related Analysis

Analysis

Data Centres and Energy Demand – What’s Needed?

The growth in data centres brings with it increased energy demands and as a result the use of power has become the number one issue for their operators globally. Australia is seen as a country that will continue to see growth in data centres and Morgan Stanley Research has taken a detailed look at both the anticipated growth in data centres in Australia and what it might mean for our grid. We take a closer look.

Jun 27 2024
Analysis

Green certification key to Government’s climate ambitions

The energy transition is creating surging corporate demand, both domestically and internationally, for renewable electricity. But with growing scrutiny towards greenwashing, it is critical all green electricity claims are verifiable and credible. The Federal Government has designed a policy to perform this function but in recent months the timing of its implementation has come under some doubt. We take a closer look.

Jun 27 2024
Analysis

Energy regulation: A tale of increasing overload?

The energy sector is seeing an increase in regulation, with the retail laws and rules seemingly being changed year on year. This has led to old, overlapping or obsolete regulation not being removed, making it difficult for retailers to comply with, and regulators to enforce these rules and laws. We take a look at how overregulation is affecting customers and the cost of electricity.

Jun 20 2024
GET IN TOUCH
Do you have a question or comment for AEC?

Send an email with your question or comment, and include your name and a short message and we'll get back to you shortly.

Call Us
+61 (3) 9205 3100