Everyone knows what new renewables are – until you have to define it

Sometimes the simplest questions are the hardest to answer, as the Australian Government is finding in its efforts to require data centres to procure new renewable generation and firming. 

The predicament hinges on whether a strict or flexible definition of “new” better brings forward investment. Policymakers will need to get it right because the stakes are high, with the recently proposed data centre rules exposing non-compliant data centres to financial penalties and even directions to cut their power demand. 

Let’s take a look at what is being considered.  

 

The different ways to define “new”  

Energy ministers have asked policymakers to develop policy options to ensure “data centres invest in new, additional renewable generation”.  

There are different ways to determine whether a project is “new” although it generally revolves around a principle of additionality: that the project would not have occurred otherwise.  

The table below summarises how some related climate or energy policies establish newness.  

 

Policy 

Definition  

Renewable Energy Target (RET) 

The RET uses a baseline year of 1997 to determine whether renewable generation is new. Renewable generation produced before 1997 is ineligible to participate and cannot produce Large-scale Generation Certificates (LGCs).   

 

Australian Carbon Credit Units  

To produce carbon credits, projects must satisfy an “additionality” test: the project should result in carbon abatement that is unlikely to occur in the ordinary course of events. 

 

RE 100  

 

 

Procured renewable electricity must come from generation assets commissioned or repowered within the preceding 15 years.  

 

Ireland’s data centre energy rules  

 

Generation is additional so long as it has not been previously contracted or committed and is outside any government support schemes.  

 

 

What makes defining “new” so particularly complex here is the inclusion of a variable – i.e. that generation must be new relative to the age of the data centre.  

 

Is there an attribution test? 

There is hesitancy towards requirements to establish a causal link between a data centre project and new generation being built principally because it could delay rather than support renewable investment. 

It would essentially send a signal to prospective developers to hold off investing in new renewables or firming until they have an offtake agreement in place with a data centre. This would not be a desirable outcome and renewable and firming projects that are built in anticipation of new demand coming online should be rewarded.  

 

What about a time test? 

The alternative to attribution is setting a date or baseline to separate old from new. The obvious question here is what year. 

The strictest option, being the year the policy becomes law (likely 2027), risks undesirable consequences. This is because it would stifle investment until the policy is officially law and would exclude renewable and firming projects that have already started their development in response to forecasted data centre demand.  

Another option is to set the year in accordance with when the policy was first announced, which would be 2026. This would better reward early moving projects but could still encourage project developers to “hold off” until they are sure about their eligibility under the rules.  

In terms of when a project is considered to have started, the AEMC’s data centre advice recommends “flexibility here, with renewable and firming projects that are not yet at financial close able to be counted as additional”. 

This definition seems to be gaining traction. It has been adopted in the NSW Data Centre Guidelines while the proposed contracting obligation says “one option for defining ‘new’ is based on when the underlying asset has reached a final investment decision (FID) or financial close (FC), as this will help to ensure that the investment is additional”.  

Even so, some stakeholders including the Clean Energy Council say it is not without complication because it “may be challenging to reliably observe in practice, particularly in scenarios in which data centres are being financed on-balance sheet by investors that are not publicly listed”. They instead suggest a project achieving ‘Committed’ status on AEMO’s Generation Information page as evidence of additionality.  

No matter the year or approach there remains an inescapable problem: the time mismatch between how long it takes for a new renewable project to be built (often 5 to 7 years) versus a data centre (roughly 1 to 2 years). This means new renewables will not come online until many years after the data centre is running, creating a need for phasing requirements that existing renewables can fulfill.  

 

How does the age of the data centre matter?  

At this stage, it is not entirely clear. The rule change proposal only says that: “once an asset is declared ‘new’ relative to the age of the data centre, this status will be considered enduring for the asset”. 

This clarifies that a data centre can use the same new generation asset for its life, but leaves the AEMC to resolve other key questions: 

  • Will the FID date (if pursued) of new generation need to be within a certain time window of the data centre’s FID? 
  • If existing data centres are captured, then are they also required to procure new renewables? 
  • What would the baseline year be for existing data centres?  

Coverage of existing data centres reduces the risk of loopholes, but it also poses some philosophical questions about purpose given their demand is already being served and is not placing pressure on adequacy of supply.  

 

Does the firming need to be new too?  

Yes, at least according to the Minister’s rule change proposal. Even though firming is technology agnostic, it rules out using existing plants: “While some jurisdictions have excess firming capacity provided by legacy plant, if these existing sources of generation are used to meet new data centre load that will, by definition, negatively impact the supply-demand balance, resulting in higher prices and the potential for system inadequacy”.  

Once open to consultation, it is expected there will be considerable scrutiny over the contention that use of excess firming capacity could negatively impact prices.  

 

What is the eligibility of projects receiving government support? 

Unlike some overseas jurisdictions, the Australian Government is intending to allow renewable projects that receive government funding (e.g. through the Capacity Investment Scheme) to be eligible. Minister Bowen said in a recent speech that: “An agreement from a proposed wind farm for example that may have received support under the Capacity Investment Scheme or a state scheme and environmental approvals, but has not yet reached final investment decision stage, could qualify as new additional renewable energy”.    

The AEMC’s advice confirmed that additionality “includes projects that have won CIS contract but would benefit from additional financial support from data centres”. 

 

Is there any role for existing renewable generation?  

Existing renewables will play an important role in supporting the greenness of data centres due to expected phase-in or bridging requirements. But there is another, arguably bigger, consideration policymakers should give their attention to.  

Existing assets can and do undergo expansions, life extensions, retrofitting, and refurbishment to improve their efficiency and/or total capacity. Depending on the market circumstances, leveraging expanded capacity from an existing renewable generator could be cheaper and quicker than building a new project.  

But incentives for existing renewables to pursue such enhancements are reduced if they cannot supply a major new load. For this reason, the AEC has suggested the meaning of “new” should be flexible enough to reward existing plants that undertake expansions or refurbishments.   

 

Sometimes less is more  

The definition of “new” is only one of a hundred questions policymakers must resolve to get Australia’s data centre energy rules in place by next year. 

With the policy focus centering on managing affordability impacts, it is important that any new rules complement the NEM’s existing market-based features, which are designed to incentivise the reliable supply of electricity to meet demand at lowest cost. Rules that are duplicative or too administratively burdensome will only make efficient investment harder.  

Policymakers will also need to remain conscious of the ongoing implementation of the NEM Review recommendations, and especially how these rules will interact with the Electricity Services Entry Mechanism (ESEM). Where possible, renewable investment should be pursued through the ESEM and supporting energy market processes rather than a second set of rules.  

It goes without saying, there is still much to play out.